Infrabel completes 12-year upgrade project of Belgian port shunting yard

Belgian infrastructure manager Infrabel on Monday inaugurated the new shunting yard in the Port of Zeebrugge. The project, labelled the ‘biggest in the history of the port’ by the various stakeholders, took 12 years to complete at a cost of 133 million euros. More than 18 kilometres of new tracks were installed.

The new shunting yard of the port of Zeebrugge consists of two large track bundles: the departure and arrival bundle Zwankendamme and the shunting bundle Zeebrugge. Zwankendamme’s infrastructure had already been modernised and was completed at the end of 2018. Now the finishing touches have also been made to the Zeebrugge shunting bundle.

The entire overhaul saw the installation of 45 switches, 27,500 new sleepers, 16 kilometres worth of overhead lines and 60 kilometres of cables. There are now 18 tracks in total. The Zeebrugge marshalling yard has eight tracks, four of which have overhead wires. Three tracks in the bundle are long tracks, where trains of up to 750 meters can be received.

The project will free up track capacity @ 2023, Matthias Vanheerentals / ProMedia

The Zwankendamme bundle has ten electrified tracks, four of which are long tracks. In addition to these tracks, there is a separate bundle of 4 tracks where Infrabel customers can temporarily park their locomotives. In the past, locomotives were parked in the shunting yard, which resulted in a loss of capacity. The new infrastructure also has an automatic hill installation and automatically operated switches. Such a system speeds up the shunting and composition of freight trains.

Both track bundles are now located behind each other, while they used to be on the other side of the main Bruges-Zeebrugge track. Now that trains have to cross this line much less often, more capacity will become available and freight trains will have to make fewer shunting movements.

This article was originally published on RailTech.com the organiser of RailTech Belgium.

morenews

First edition of RailTech Belgium opens registration

The first speakers of the conference are confirmed, among which Georges Gilkinet, Deputy Prime Minister and Minister of Mobility in Belgium, Michel Ruesen, Managing Director of the ERTMS Users Group and Thierry Vanelslander, professor at the Department of Transport and Regional Economics of the University of Antwerp. The conference topics The morning conference will look… Read more ›

Major improvements for Brussels’ public transport infrastructure planned for 2023

The work will require 3,150 metres of track beams, 134 prefabricated track modules and more than 400 intermediate precast slabs, as well as 5,000 square metres of bricks embedded in those modules, almost 1,900 metres of drainage trenches, more than 7,500 concrete sleepers and as many thousands of accessories for fixing and protecting the tracks…. Read more ›

ETCS rollout in Belgium continues unabated

With more than 2,000 kilometres, the level ETCS1 FS is the most prevalent on the Belgian network, followed by ETCS1 LS. This article was originally published on RailTech.com the organiser of RailTech Belgium.